Dubai off-plan delivery observatory

How many off-plan projects in Dubai are completed after the end date declared at the Dubai Land Department, and by how much? This observatory answers from the DLD's official project register alone: 1,579 completed and 1,061 active projects, compared one by one. The figures, tables and charts are free to reuse with credit and a link.

Updated November 23, 2026 · DLD project register as of November 1, 2026 · Use this data · CSV

  • 22.5%of active projects are past their declared end date
  • 59,689units and villas in those projects
  • 6.3 monthsmedian gap with the declared date
  • 55.4%of projects completed since 2025 finished after the declared date

Key figures to quote

  • 239 of the 1,061 active property projects in Dubai with a declared end date (22.5%) had passed that date on November 1, 2026, according to the DLD project register as of November 1, 2026.
  • These 239 projects hold 59,689 units and villas, 20.3% of all units and villas in active projects, according to the DLD project register as of November 1, 2026.
  • The median gap with the declared end date is 6.3 months for these projects; 49 of them are more than 12 months past it, according to the DLD project register as of November 1, 2026.
  • Of these projects, 43 show construction progress of 90% or more and 61 are below 50%, according to the DLD project register as of November 1, 2026.
  • 55.4% of projects completed since 1 January 2025 (133 of 240) were completed after their end date declared at the DLD, with a median gap of 6.9 months, according to the DLD project register as of November 1, 2026.
  • Across the whole register, 231 of 1,579 completed projects (14.6%) carry a completion date later than their declared end date; for another 1,102, both dates are the same day, according to the DLD project register as of November 1, 2026.

Source: Dubai Off-Plan Delivery Observatory, Cevitas Real Estate, based on the Dubai Land Department project register as of November 1, 2026.

Active projects past their declared end date

As of November 1, 2026, the register lists 1,061 active projects with a declared end date. For 239 of them that date has passed; 822 have an end date still ahead. The chart splits the 239 projects by the gap between their declared end date and November 1, 2026.

Active projects by gap with the declared end date3 months or less523 to 6 months546 to 12 months8412 to 24 months30More than 24 months19
Active projects past their declared end date, by gap as of November 1, 2026. Source: DLD project register; Cevitas calculation.
Gap with the declared end dateProjectsShare
3 months or less5221.8%
3 to 6 months5422.6%
6 to 12 months8435.1%
12 to 24 months3012.6%
More than 24 months197.9%

Progress is the figure from the latest inspection recorded in the register. A project at 90% or more is at the finishing stage; below 50%, a large part of the works remains.

Progress in the registerProjectsShare
90% or more4318.0%
50% to 90%13556.5%
Below 50%6125.5%

Units and villas: 56,395 units and 3,294 villas in the projects past their date, out of 294,368 units and villas across all active projects analysed.

Completed projects: completion date and declared end date

For each completed project, we compare the completion date in the register with the declared end date, to the day. Three cases: completed before the date, on the same day, or after it. The median gap is computed on the projects completed after the date.

Completed projectsProjectsBefore the dateSame dayAfter the dateMedian gap (after)
Completed since 1 January 202524055 (22.9%)52 (21.7%)133 (55.4%)6.9 months
All completed projects in the register1,579246 (15.6%)1,102 (69.8%)231 (14.6%)6.6 months

One important limit: from 2010 to 2024, 77.8% of completed projects (979 of 1,259) have a declared end date exactly equal to their completion date. For them, the register does not show whether the originally announced date was met. For projects completed in 2025 and 2026, the two dates differ in 78.3% of cases, which is why we highlight that period.

Completed projects by year and position against the declared end date050100150200201020122014201620182020202220242026*

Completed before the declared dateSame dayAfter the declared date

Completed projects by completion year, 2010 to 2026 (* up to November 1, 2026). Source: DLD project register; Cevitas calculation.
Completion yearProjectsBefore the dateSame dayAfter the dateMedian gap (after)
2010834790—
2011609501—
201244431914.3 months
2013567381123.0 months
2014781553103.2 months
2015934732144.9 months
2016732140122.6 months
201766945125.4 months
2018608484—
20199019683—
2020899782—
202183156269.2 months
20221371411850.7 months
202312921243—
202411821133—
20251152050455.8 months
2026 (to 01/11/2026)125352887.4 months

Median gap shown from 5 projects completed after the date. 80 projects completed before 2010 are in the totals but not in the chart.

By launch year

For each project start year, we keep the projects whose declared end date had passed by November 1, 2026: completed projects, and active projects past their date. Active projects whose date is still ahead appear in the table but not in the chart.

Projects whose declared end date has passed, by launch year0%25%50%75%100%≤200920102013201420152016201720182019202020212022202320242025

Completed before the dateCompleted on the same dayCompleted after the dateActive, date passed

Split (%) of projects whose declared end date has passed, by project start year (years with at least 20 such projects). Source: DLD project register as of November 1, 2026; Cevitas calculation.
LaunchCompletedof which after the dateActiveof which date passedUnits and villas (active, date passed)
≤200942239772,277
2010344000
201110311343
201216211145
2013737100
201412517331,073
2015936221,393
20161061122285
20171489200
201877144740
201967121428
202034111407
20218512431,005
20221344040317,177
2023109521156013,717
202443262869823,814
202530513256,885
2026007700

Launch year = year of the project start date in the register (project_start_date).

By DLD area

Area = the "area" field of the project register (the DLD's official division, which does not always match the marketing name: Jumeirah Village Circle, for example, is registered in Al Barsha South Fourth). An area or developer is listed from 10 completed or 10 active projects. A share is shown only when it rests on at least 10 projects, a median gap on at least 5; otherwise "—". Rows are sorted by number of projects analysed.

DLD areaCompleted projectsCompleted after the declared dateMedian gapActive projectsDate passed on 01/11/2026Units and villas concerned
Al Barsha South Fourth23333 (14.2%)4.6 months10141 (40.6%)10,486
Business Bay11118 (16.2%)6.3 months3312 (36.4%)4,843
Al Merkadh1177 (6.0%)1.0 months122 (16.7%)455
Wadi Al Safa 5505 (10.0%)23.0 months709 (12.9%)1,633
Madinat Al Mataar344 (11.8%)—8421 (25.0%)9,813
Jabal Ali First6416 (25.0%)3.9 months5010 (20.0%)1,165
Palm Deira3——9313 (14.0%)1,281
Marsa Dubai687 (10.3%)6.8 months203 (15.0%)711
Wadi Al Safa 3277 (25.9%)7.5 months5711 (19.3%)820
Al Hebiah Fourth608 (13.3%)8.8 months2010 (50.0%)3,603
Al Thanyah Fifth563 (5.4%)—167 (43.8%)3,223
Al Barshaa South Third5018 (36.0%)6.6 months197 (36.8%)2,475
Nadd Hessa556 (10.9%)17.4 months113 (27.3%)967
Wadi Al Safa 2552 (3.6%)—9——
Hadaeq Sheikh Mohammed Bin Rashid436 (14.0%)5.2 months201 (5.0%)129
Burj Khalifa436 (14.0%)7.0 months142 (14.3%)733
Al Barsha South Fifth278 (29.6%)6.4 months245 (20.8%)547
Palm Jumeirah377 (18.9%)7.7 months144 (28.6%)201
Al Hebiah Third432 (4.7%)—6——
Me'Aisem First325 (15.6%)12.0 months174 (23.5%)2,054
Al Khairan First310 (0.0%)—120 (0.0%)0
Warsan Fourth184 (22.2%)—215 (23.8%)487
Madinat Hind 4323 (9.4%)—6——
Al Jadaf235 (21.7%)5.8 months124 (33.3%)1,140
Al Satwa5—3.2 months2913 (44.8%)1,193
Dubai Investment Park Second3——300 (0.0%)0
Al Yelayiss 2202 (10.0%)—121 (8.3%)576
Al Wasl203 (15.0%)—114 (36.4%)861
Nad Al Shiba First177 (41.2%)4.0 months145 (35.7%)406
Al Yelayiss 19——180 (0.0%)0
Madinat Dubai Almelaheyah3——243 (12.5%)932
Al Warsan First202 (10.0%)—6——
Al Hebiah Fifth9—8.4 months159 (60.0%)178
Wadi Al Safa 7192 (10.5%)—5——
Al Yufrah 16——150 (0.0%)0
Al Hebiah Second104 (40.0%)—8——
Al Hebiah First6——112 (18.2%)480
Palm Jabal Ali0——170 (0.0%)0
Bukadra0——150 (0.0%)0
Saih Shuaib 25——101 (10.0%)84
Al Thanayah Fourth142 (14.3%)—0——
Al Hebiah Sixth132 (15.4%)—0——
Al Thanyah First111 (9.1%)—2——
Al Thanyah Third121 (8.3%)—0——
Jumeirah First101 (10.0%)—1——

45 areas. Source: DLD project register as of November 1, 2026; Cevitas calculation.

By registered developer

Developer = the company registered as the project's developer (not the community's master developer). One group can appear under several companies. These figures describe recorded dates: they do not say why a date was passed (approved extension, project change, site conditions) and are not an assessment of any developer. An area or developer is listed from 10 completed or 10 active projects. A share is shown only when it rests on at least 10 projects, a median gap on at least 5; otherwise "—". Rows are sorted by number of projects analysed.

Developer (registered name)Completed projectsCompleted after the declared dateMedian gapActive projectsDate passed on 01/11/2026Units and villas concerned
Emaar Development P.J.S.C.570 (0.0%)—410 (0.0%)0
Binghatti Developers FZE376 (16.2%)5.9 months2314 (60.9%)10,231
Emaar Properties (P.J.S.C)507 (14.0%)12.0 months4——
Dubai Hills Estate L.L.C353 (8.6%)—150 (0.0%)0
DAMAC Crescent Properties432 (4.7%)—6——
Front Line Investment Management L.L.C323 (9.4%)—6——
District One - FZ360 (0.0%)—1——
Deyaar Development (P.J.S.C)274 (14.8%)—7——
Al Mazaya Real Estate FZ-LLC332 (6.1%)—0——
Danube Properties Development L.L.C193 (15.8%)—114 (36.4%)2,830
Sobha L.L.C173 (17.6%)—130 (0.0%)0
Ellington Properties Development L.L.C151 (6.7%)—126 (50.0%)989
Emaar Dubai South DWC LLC121 (8.3%)—130 (0.0%)0
Nshama Properties Owned by Nshmi Development One Person Company L.L.C132 (15.4%)—120 (0.0%)0
Tiger Properties186 (33.3%)6.4 months5——
Island Oasis Properties9—8.4 months148 (57.1%)0
Dubai South Properties DWC LLC130 (0.0%)—9——
Dubai Creek Harbour L.L.C120 (0.0%)—100 (0.0%)0
The Lagoons Phase One L.L.C190 (0.0%)—2——
DAMAC Properties Co (L.L.C)201 (5.0%)—0——
North Dubailand Projects L.L.C170 (0.0%)—2——
Citywalk Residential 1 L.L.C153 (20.0%)—4——
DAMAC Elite Investment Co. L.L.C0——180 (0.0%)0
Gulf General Investments Co. (p.s.c)181 (5.6%)—0——
The Palm - Jebel Ali Co. (L.L.C)0——170 (0.0%)0
DAMAC MRY Investment L.L.C0——170 (0.0%)0
Imtiaz Real Estate Investment & Development L.L.C5——113 (27.3%)524
SAMANA International Real Estate Development L.L.C5——102 (20.0%)498
T F G Real Estate L.L.C141 (7.1%)—0——
Select Global Development L.L.C146 (42.9%)6.7 months0——
Obj1 Real Estate Development L.L.C0——133 (23.1%)587
Mina Rashid Properties L.L.C1——111 (9.1%)155
DAMAC Development(l L C)125 (41.7%)2.6 months0——
Diamond Developers Co.limited123 (25.0%)—0——
DAMAC Star Properties (l L C)122 (16.7%)—0——
MDN Real Estate L.L.C122 (16.7%)—0——
Jumeirah Golf Estates L.L.C113 (27.3%)—0——
SAMANA Signature Real Estate Developments L.L.C0——101 (10.0%)441

38 developers. The table does not include every developer in the register: projects of those not listed remain counted in the totals, areas and years. Source: DLD project and developer registers as of November 1, 2026; Cevitas calculation.

Reading these figures

  • The declared end date can change. The register keeps only the latest value. The gap measured here relates to that date, not necessarily to the date announced at launch or to the one in your sale and purchase agreement (SPA).
  • Units and villas. The register counts each project's units (apartments, but also offices or shops in a mixed-use project) and villas, without separating homes from the rest.
  • No cause is recorded. A passed date can reflect an approved extension, a project change or site constraints. The register does not say, and neither does this page.
  • For a given project, check its status and progress with the DLD's Real Estate Project Status Enquiry service (also in the Dubai REST app), or on our off-plan project pages, which carry the register data. What the law provides when handover runs past the planned date is covered in our article on off-plan buyer rights.

Use this data

Journalists, researchers, bloggers, teachers: you may freely reuse the figures, tables and charts of this observatory in an article, a study, a presentation or on social media, on two conditions: credit the source and link to this page. Credit line to copy:

Source: Dubai Off-Plan Delivery Observatory, Cevitas Real Estate, based on the Dubai Land Department project register as of November 1, 2026 — https://www.cevitas.ae/en/dubai-off-plan-delivery-observatory

HTML version, with the link:

<a href="https://www.cevitas.ae/en/dubai-off-plan-delivery-observatory">Dubai Off-Plan Delivery Observatory (Cevitas Real Estate, DLD data)</a>

The underlying data is published by the Dubai Land Department under the Dubai Open Data Licence (project register, developer register). Questions on the method or interview requests: ahmed@cevitas.ae · +971 55 772 2710.

Download the aggregated data (CSV)

Methodology and sources

Source: Dubai Land Department "Projects" register (data.dubai, dataset 467654) and "Developers" register (dataset 462802), files projects_2026-11-01_18-17-23_0001.csv.gz, developers_2026-11-01_18-10-29_0001.csv.gz, extract as of November 1, 2026. Dubai Open Data Licence. No other source is used.

Scope: the 3,474 projects in the extract, of which 1,684 completed (status FINISHED) and 1,237 active (ACTIVE). The other 553 (not started, pending, conditional activation, frozen) are out of scope. 1,060 of the 1,061 active projects analysed have a registered escrow account, the condition for selling off-plan in Dubai.

Definitions: declared end date = project_end_date; completion date = completion_date; compared to the day. An active project is "past its date" if its declared end date is before November 1, 2026. Gaps are in months (days / 30.4375). Units and villas = no_of_units + no_of_villas; plots (no_of_lands) are not counted.

Rows left out because a field is missing or ambiguous. Completed projects (105): no declared end date: 69 ; cancellation date filled in: 15 ; end date before start date: 12 ; completion date before start date: 7 ; no completion date: 2. Active projects (176): no declared end date: 164 ; cancellation date filled in: 12. This leaves 1,579 completed and 1,061 active projects.

Limits: the register keeps only the latest declared end date; from 2010 to 2024, most completed projects have an end date identical to their completion date, so the gap with the original date cannot be measured. Whole-register figures should be read as a floor, and the indicator on projects completed since 2025 as the most telling. Progress is the figure from the latest recorded inspection.

Areas and developers: area = area_name_en; developer = the project's developer_number and its name in the developer register. Thresholds: 10 projects to show a share, 5 projects for a median gap. Sorted by number of projects analysed.

Reproducible calculation: scripts/dld/aggregate_deliveries.py reads data/dld/registry.json (built by scripts/dld/aggregate_registry.py from the raw DLD files) and checks that every total adds up. The page and the CSV are regenerated with each register update.

Further reading

Frequently asked questions

How many off-plan projects in Dubai are past their declared end date?

As of November 1, 2026, 239 of the 1,061 active projects with a declared end date had passed it (22.5%), with 59,689 units and villas, according to the Dubai Land Department project register.

What share of off-plan projects is completed after the announced date?

Of the projects completed since 1 January 2025, 55.4% (133 of 240) were completed after their end date declared at the DLD. Across the whole register the share is 14.6%, but it understates the gap: for 1,102 projects, the recorded end date is exactly the completion date.

By how many months is the declared end date passed?

The median gap is 6.9 months for projects completed after the date since 2025, and 6.3 months for active projects past their date on November 1, 2026. 49 active projects are more than 12 months past their date.

What is the end date declared at the DLD?

It is the project end date recorded in the Dubai Land Department project register. It can be updated and the register keeps only the latest value, so it may differ from the date announced at launch and from the one in your sale and purchase agreement (SPA).

Why do so many projects have an end date equal to their completion date?

From 2010 to 2024, 77.8% of completed projects have a declared end date identical to their completion date. The register does not say why; these projects cannot show whether the original date was met. This is why the observatory highlights projects completed since 2025, whose two dates usually differ.

How can I check the progress of an off-plan project in Dubai?

The Dubai Land Department's Real Estate Project Status Enquiry service, also in the Dubai REST app, gives the status and completion percentage of a registered project. Our off-plan project pages also carry the register data: progress, declared end date and developer.

What happens to buyers when the end date is passed?

Payments go into the project's escrow account, which Law No. 8 of 2007 reserves for its construction. Any compensation depends on the clauses of the sale and purchase agreement (SPA): the law sets no scale. Our article on off-plan buyer rights covers the remedies.

Can I reuse the figures of this observatory?

Yes, freely, crediting "Source: Dubai Off-Plan Delivery Observatory, Cevitas Real Estate, based on the Dubai Land Department project register as of November 1, 2026" with a link to this page. The aggregated data can be downloaded as CSV.

To prepare your purchase, read our guide to investing in Dubai real estate and our UAE real estate guide.