Dubai off-plan delivery observatory
How many off-plan projects in Dubai are completed after the end date declared at the Dubai Land Department, and by how much? This observatory answers from the DLD's official project register alone: 1,579 completed and 1,061 active projects, compared one by one. The figures, tables and charts are free to reuse with credit and a link.
Updated November 23, 2026 · DLD project register as of November 1, 2026 · Use this data · CSV
- 22.5%of active projects are past their declared end date
- 59,689units and villas in those projects
- 6.3 monthsmedian gap with the declared date
- 55.4%of projects completed since 2025 finished after the declared date
Key figures to quote
- 239 of the 1,061 active property projects in Dubai with a declared end date (22.5%) had passed that date on November 1, 2026, according to the DLD project register as of November 1, 2026.
- These 239 projects hold 59,689 units and villas, 20.3% of all units and villas in active projects, according to the DLD project register as of November 1, 2026.
- The median gap with the declared end date is 6.3 months for these projects; 49 of them are more than 12 months past it, according to the DLD project register as of November 1, 2026.
- Of these projects, 43 show construction progress of 90% or more and 61 are below 50%, according to the DLD project register as of November 1, 2026.
- 55.4% of projects completed since 1 January 2025 (133 of 240) were completed after their end date declared at the DLD, with a median gap of 6.9 months, according to the DLD project register as of November 1, 2026.
- Across the whole register, 231 of 1,579 completed projects (14.6%) carry a completion date later than their declared end date; for another 1,102, both dates are the same day, according to the DLD project register as of November 1, 2026.
Source: Dubai Off-Plan Delivery Observatory, Cevitas Real Estate, based on the Dubai Land Department project register as of November 1, 2026.
Active projects past their declared end date
As of November 1, 2026, the register lists 1,061 active projects with a declared end date. For 239 of them that date has passed; 822 have an end date still ahead. The chart splits the 239 projects by the gap between their declared end date and November 1, 2026.
| Gap with the declared end date | Projects | Share |
|---|---|---|
| 3 months or less | 52 | 21.8% |
| 3 to 6 months | 54 | 22.6% |
| 6 to 12 months | 84 | 35.1% |
| 12 to 24 months | 30 | 12.6% |
| More than 24 months | 19 | 7.9% |
Progress is the figure from the latest inspection recorded in the register. A project at 90% or more is at the finishing stage; below 50%, a large part of the works remains.
| Progress in the register | Projects | Share |
|---|---|---|
| 90% or more | 43 | 18.0% |
| 50% to 90% | 135 | 56.5% |
| Below 50% | 61 | 25.5% |
Units and villas: 56,395 units and 3,294 villas in the projects past their date, out of 294,368 units and villas across all active projects analysed.
Completed projects: completion date and declared end date
For each completed project, we compare the completion date in the register with the declared end date, to the day. Three cases: completed before the date, on the same day, or after it. The median gap is computed on the projects completed after the date.
| Completed projects | Projects | Before the date | Same day | After the date | Median gap (after) |
|---|---|---|---|---|---|
| Completed since 1 January 2025 | 240 | 55 (22.9%) | 52 (21.7%) | 133 (55.4%) | 6.9 months |
| All completed projects in the register | 1,579 | 246 (15.6%) | 1,102 (69.8%) | 231 (14.6%) | 6.6 months |
One important limit: from 2010 to 2024, 77.8% of completed projects (979 of 1,259) have a declared end date exactly equal to their completion date. For them, the register does not show whether the originally announced date was met. For projects completed in 2025 and 2026, the two dates differ in 78.3% of cases, which is why we highlight that period.
Completed before the declared dateSame dayAfter the declared date
| Completion year | Projects | Before the date | Same day | After the date | Median gap (after) |
|---|---|---|---|---|---|
| 2010 | 83 | 4 | 79 | 0 | — |
| 2011 | 60 | 9 | 50 | 1 | — |
| 2012 | 44 | 4 | 31 | 9 | 14.3 months |
| 2013 | 56 | 7 | 38 | 11 | 23.0 months |
| 2014 | 78 | 15 | 53 | 10 | 3.2 months |
| 2015 | 93 | 47 | 32 | 14 | 4.9 months |
| 2016 | 73 | 21 | 40 | 12 | 2.6 months |
| 2017 | 66 | 9 | 45 | 12 | 5.4 months |
| 2018 | 60 | 8 | 48 | 4 | — |
| 2019 | 90 | 19 | 68 | 3 | — |
| 2020 | 89 | 9 | 78 | 2 | — |
| 2021 | 83 | 15 | 62 | 6 | 9.2 months |
| 2022 | 137 | 14 | 118 | 5 | 0.7 months |
| 2023 | 129 | 2 | 124 | 3 | — |
| 2024 | 118 | 2 | 113 | 3 | — |
| 2025 | 115 | 20 | 50 | 45 | 5.8 months |
| 2026 (to 01/11/2026) | 125 | 35 | 2 | 88 | 7.4 months |
Median gap shown from 5 projects completed after the date. 80 projects completed before 2010 are in the totals but not in the chart.
By launch year
For each project start year, we keep the projects whose declared end date had passed by November 1, 2026: completed projects, and active projects past their date. Active projects whose date is still ahead appear in the table but not in the chart.
Completed before the dateCompleted on the same dayCompleted after the dateActive, date passed
| Launch | Completed | of which after the date | Active | of which date passed | Units and villas (active, date passed) |
|---|---|---|---|---|---|
| ≤2009 | 422 | 39 | 7 | 7 | 2,277 |
| 2010 | 34 | 4 | 0 | 0 | 0 |
| 2011 | 10 | 3 | 1 | 1 | 343 |
| 2012 | 16 | 2 | 1 | 1 | 145 |
| 2013 | 73 | 7 | 1 | 0 | 0 |
| 2014 | 125 | 17 | 3 | 3 | 1,073 |
| 2015 | 93 | 6 | 2 | 2 | 1,393 |
| 2016 | 106 | 11 | 2 | 2 | 285 |
| 2017 | 148 | 9 | 2 | 0 | 0 |
| 2018 | 77 | 1 | 4 | 4 | 740 |
| 2019 | 67 | 1 | 2 | 1 | 428 |
| 2020 | 34 | 1 | 1 | 1 | 407 |
| 2021 | 85 | 12 | 4 | 3 | 1,005 |
| 2022 | 134 | 40 | 40 | 31 | 7,177 |
| 2023 | 109 | 52 | 115 | 60 | 13,717 |
| 2024 | 43 | 26 | 286 | 98 | 23,814 |
| 2025 | 3 | 0 | 513 | 25 | 6,885 |
| 2026 | 0 | 0 | 77 | 0 | 0 |
Launch year = year of the project start date in the register (project_start_date).
By DLD area
Area = the "area" field of the project register (the DLD's official division, which does not always match the marketing name: Jumeirah Village Circle, for example, is registered in Al Barsha South Fourth). An area or developer is listed from 10 completed or 10 active projects. A share is shown only when it rests on at least 10 projects, a median gap on at least 5; otherwise "—". Rows are sorted by number of projects analysed.
| DLD area | Completed projects | Completed after the declared date | Median gap | Active projects | Date passed on 01/11/2026 | Units and villas concerned |
|---|---|---|---|---|---|---|
| Al Barsha South Fourth | 233 | 33 (14.2%) | 4.6 months | 101 | 41 (40.6%) | 10,486 |
| Business Bay | 111 | 18 (16.2%) | 6.3 months | 33 | 12 (36.4%) | 4,843 |
| Al Merkadh | 117 | 7 (6.0%) | 1.0 months | 12 | 2 (16.7%) | 455 |
| Wadi Al Safa 5 | 50 | 5 (10.0%) | 23.0 months | 70 | 9 (12.9%) | 1,633 |
| Madinat Al Mataar | 34 | 4 (11.8%) | — | 84 | 21 (25.0%) | 9,813 |
| Jabal Ali First | 64 | 16 (25.0%) | 3.9 months | 50 | 10 (20.0%) | 1,165 |
| Palm Deira | 3 | — | — | 93 | 13 (14.0%) | 1,281 |
| Marsa Dubai | 68 | 7 (10.3%) | 6.8 months | 20 | 3 (15.0%) | 711 |
| Wadi Al Safa 3 | 27 | 7 (25.9%) | 7.5 months | 57 | 11 (19.3%) | 820 |
| Al Hebiah Fourth | 60 | 8 (13.3%) | 8.8 months | 20 | 10 (50.0%) | 3,603 |
| Al Thanyah Fifth | 56 | 3 (5.4%) | — | 16 | 7 (43.8%) | 3,223 |
| Al Barshaa South Third | 50 | 18 (36.0%) | 6.6 months | 19 | 7 (36.8%) | 2,475 |
| Nadd Hessa | 55 | 6 (10.9%) | 17.4 months | 11 | 3 (27.3%) | 967 |
| Wadi Al Safa 2 | 55 | 2 (3.6%) | — | 9 | — | — |
| Hadaeq Sheikh Mohammed Bin Rashid | 43 | 6 (14.0%) | 5.2 months | 20 | 1 (5.0%) | 129 |
| Burj Khalifa | 43 | 6 (14.0%) | 7.0 months | 14 | 2 (14.3%) | 733 |
| Al Barsha South Fifth | 27 | 8 (29.6%) | 6.4 months | 24 | 5 (20.8%) | 547 |
| Palm Jumeirah | 37 | 7 (18.9%) | 7.7 months | 14 | 4 (28.6%) | 201 |
| Al Hebiah Third | 43 | 2 (4.7%) | — | 6 | — | — |
| Me'Aisem First | 32 | 5 (15.6%) | 12.0 months | 17 | 4 (23.5%) | 2,054 |
| Al Khairan First | 31 | 0 (0.0%) | — | 12 | 0 (0.0%) | 0 |
| Warsan Fourth | 18 | 4 (22.2%) | — | 21 | 5 (23.8%) | 487 |
| Madinat Hind 4 | 32 | 3 (9.4%) | — | 6 | — | — |
| Al Jadaf | 23 | 5 (21.7%) | 5.8 months | 12 | 4 (33.3%) | 1,140 |
| Al Satwa | 5 | — | 3.2 months | 29 | 13 (44.8%) | 1,193 |
| Dubai Investment Park Second | 3 | — | — | 30 | 0 (0.0%) | 0 |
| Al Yelayiss 2 | 20 | 2 (10.0%) | — | 12 | 1 (8.3%) | 576 |
| Al Wasl | 20 | 3 (15.0%) | — | 11 | 4 (36.4%) | 861 |
| Nad Al Shiba First | 17 | 7 (41.2%) | 4.0 months | 14 | 5 (35.7%) | 406 |
| Al Yelayiss 1 | 9 | — | — | 18 | 0 (0.0%) | 0 |
| Madinat Dubai Almelaheyah | 3 | — | — | 24 | 3 (12.5%) | 932 |
| Al Warsan First | 20 | 2 (10.0%) | — | 6 | — | — |
| Al Hebiah Fifth | 9 | — | 8.4 months | 15 | 9 (60.0%) | 178 |
| Wadi Al Safa 7 | 19 | 2 (10.5%) | — | 5 | — | — |
| Al Yufrah 1 | 6 | — | — | 15 | 0 (0.0%) | 0 |
| Al Hebiah Second | 10 | 4 (40.0%) | — | 8 | — | — |
| Al Hebiah First | 6 | — | — | 11 | 2 (18.2%) | 480 |
| Palm Jabal Ali | 0 | — | — | 17 | 0 (0.0%) | 0 |
| Bukadra | 0 | — | — | 15 | 0 (0.0%) | 0 |
| Saih Shuaib 2 | 5 | — | — | 10 | 1 (10.0%) | 84 |
| Al Thanayah Fourth | 14 | 2 (14.3%) | — | 0 | — | — |
| Al Hebiah Sixth | 13 | 2 (15.4%) | — | 0 | — | — |
| Al Thanyah First | 11 | 1 (9.1%) | — | 2 | — | — |
| Al Thanyah Third | 12 | 1 (8.3%) | — | 0 | — | — |
| Jumeirah First | 10 | 1 (10.0%) | — | 1 | — | — |
45 areas. Source: DLD project register as of November 1, 2026; Cevitas calculation.
By registered developer
Developer = the company registered as the project's developer (not the community's master developer). One group can appear under several companies. These figures describe recorded dates: they do not say why a date was passed (approved extension, project change, site conditions) and are not an assessment of any developer. An area or developer is listed from 10 completed or 10 active projects. A share is shown only when it rests on at least 10 projects, a median gap on at least 5; otherwise "—". Rows are sorted by number of projects analysed.
| Developer (registered name) | Completed projects | Completed after the declared date | Median gap | Active projects | Date passed on 01/11/2026 | Units and villas concerned |
|---|---|---|---|---|---|---|
| Emaar Development P.J.S.C. | 57 | 0 (0.0%) | — | 41 | 0 (0.0%) | 0 |
| Binghatti Developers FZE | 37 | 6 (16.2%) | 5.9 months | 23 | 14 (60.9%) | 10,231 |
| Emaar Properties (P.J.S.C) | 50 | 7 (14.0%) | 12.0 months | 4 | — | — |
| Dubai Hills Estate L.L.C | 35 | 3 (8.6%) | — | 15 | 0 (0.0%) | 0 |
| DAMAC Crescent Properties | 43 | 2 (4.7%) | — | 6 | — | — |
| Front Line Investment Management L.L.C | 32 | 3 (9.4%) | — | 6 | — | — |
| District One - FZ | 36 | 0 (0.0%) | — | 1 | — | — |
| Deyaar Development (P.J.S.C) | 27 | 4 (14.8%) | — | 7 | — | — |
| Al Mazaya Real Estate FZ-LLC | 33 | 2 (6.1%) | — | 0 | — | — |
| Danube Properties Development L.L.C | 19 | 3 (15.8%) | — | 11 | 4 (36.4%) | 2,830 |
| Sobha L.L.C | 17 | 3 (17.6%) | — | 13 | 0 (0.0%) | 0 |
| Ellington Properties Development L.L.C | 15 | 1 (6.7%) | — | 12 | 6 (50.0%) | 989 |
| Emaar Dubai South DWC LLC | 12 | 1 (8.3%) | — | 13 | 0 (0.0%) | 0 |
| Nshama Properties Owned by Nshmi Development One Person Company L.L.C | 13 | 2 (15.4%) | — | 12 | 0 (0.0%) | 0 |
| Tiger Properties | 18 | 6 (33.3%) | 6.4 months | 5 | — | — |
| Island Oasis Properties | 9 | — | 8.4 months | 14 | 8 (57.1%) | 0 |
| Dubai South Properties DWC LLC | 13 | 0 (0.0%) | — | 9 | — | — |
| Dubai Creek Harbour L.L.C | 12 | 0 (0.0%) | — | 10 | 0 (0.0%) | 0 |
| The Lagoons Phase One L.L.C | 19 | 0 (0.0%) | — | 2 | — | — |
| DAMAC Properties Co (L.L.C) | 20 | 1 (5.0%) | — | 0 | — | — |
| North Dubailand Projects L.L.C | 17 | 0 (0.0%) | — | 2 | — | — |
| Citywalk Residential 1 L.L.C | 15 | 3 (20.0%) | — | 4 | — | — |
| DAMAC Elite Investment Co. L.L.C | 0 | — | — | 18 | 0 (0.0%) | 0 |
| Gulf General Investments Co. (p.s.c) | 18 | 1 (5.6%) | — | 0 | — | — |
| The Palm - Jebel Ali Co. (L.L.C) | 0 | — | — | 17 | 0 (0.0%) | 0 |
| DAMAC MRY Investment L.L.C | 0 | — | — | 17 | 0 (0.0%) | 0 |
| Imtiaz Real Estate Investment & Development L.L.C | 5 | — | — | 11 | 3 (27.3%) | 524 |
| SAMANA International Real Estate Development L.L.C | 5 | — | — | 10 | 2 (20.0%) | 498 |
| T F G Real Estate L.L.C | 14 | 1 (7.1%) | — | 0 | — | — |
| Select Global Development L.L.C | 14 | 6 (42.9%) | 6.7 months | 0 | — | — |
| Obj1 Real Estate Development L.L.C | 0 | — | — | 13 | 3 (23.1%) | 587 |
| Mina Rashid Properties L.L.C | 1 | — | — | 11 | 1 (9.1%) | 155 |
| DAMAC Development(l L C) | 12 | 5 (41.7%) | 2.6 months | 0 | — | — |
| Diamond Developers Co.limited | 12 | 3 (25.0%) | — | 0 | — | — |
| DAMAC Star Properties (l L C) | 12 | 2 (16.7%) | — | 0 | — | — |
| MDN Real Estate L.L.C | 12 | 2 (16.7%) | — | 0 | — | — |
| Jumeirah Golf Estates L.L.C | 11 | 3 (27.3%) | — | 0 | — | — |
| SAMANA Signature Real Estate Developments L.L.C | 0 | — | — | 10 | 1 (10.0%) | 441 |
38 developers. The table does not include every developer in the register: projects of those not listed remain counted in the totals, areas and years. Source: DLD project and developer registers as of November 1, 2026; Cevitas calculation.
Reading these figures
- The declared end date can change. The register keeps only the latest value. The gap measured here relates to that date, not necessarily to the date announced at launch or to the one in your sale and purchase agreement (SPA).
- Units and villas. The register counts each project's units (apartments, but also offices or shops in a mixed-use project) and villas, without separating homes from the rest.
- No cause is recorded. A passed date can reflect an approved extension, a project change or site constraints. The register does not say, and neither does this page.
- For a given project, check its status and progress with the DLD's Real Estate Project Status Enquiry service (also in the Dubai REST app), or on our off-plan project pages, which carry the register data. What the law provides when handover runs past the planned date is covered in our article on off-plan buyer rights.
Use this data
Journalists, researchers, bloggers, teachers: you may freely reuse the figures, tables and charts of this observatory in an article, a study, a presentation or on social media, on two conditions: credit the source and link to this page. Credit line to copy:
Source: Dubai Off-Plan Delivery Observatory, Cevitas Real Estate, based on the Dubai Land Department project register as of November 1, 2026 — https://www.cevitas.ae/en/dubai-off-plan-delivery-observatoryHTML version, with the link:
<a href="https://www.cevitas.ae/en/dubai-off-plan-delivery-observatory">Dubai Off-Plan Delivery Observatory (Cevitas Real Estate, DLD data)</a>The underlying data is published by the Dubai Land Department under the Dubai Open Data Licence (project register, developer register). Questions on the method or interview requests: ahmed@cevitas.ae · +971 55 772 2710.
Methodology and sources
Source: Dubai Land Department "Projects" register (data.dubai, dataset 467654) and "Developers" register (dataset 462802), files projects_2026-11-01_18-17-23_0001.csv.gz, developers_2026-11-01_18-10-29_0001.csv.gz, extract as of November 1, 2026. Dubai Open Data Licence. No other source is used.
Scope: the 3,474 projects in the extract, of which 1,684 completed (status FINISHED) and 1,237 active (ACTIVE). The other 553 (not started, pending, conditional activation, frozen) are out of scope. 1,060 of the 1,061 active projects analysed have a registered escrow account, the condition for selling off-plan in Dubai.
Definitions: declared end date = project_end_date; completion date = completion_date; compared to the day. An active project is "past its date" if its declared end date is before November 1, 2026. Gaps are in months (days / 30.4375). Units and villas = no_of_units + no_of_villas; plots (no_of_lands) are not counted.
Rows left out because a field is missing or ambiguous. Completed projects (105): no declared end date: 69 ; cancellation date filled in: 15 ; end date before start date: 12 ; completion date before start date: 7 ; no completion date: 2. Active projects (176): no declared end date: 164 ; cancellation date filled in: 12. This leaves 1,579 completed and 1,061 active projects.
Limits: the register keeps only the latest declared end date; from 2010 to 2024, most completed projects have an end date identical to their completion date, so the gap with the original date cannot be measured. Whole-register figures should be read as a floor, and the indicator on projects completed since 2025 as the most telling. Progress is the figure from the latest recorded inspection.
Areas and developers: area = area_name_en; developer = the project's developer_number and its name in the developer register. Thresholds: 10 projects to show a share, 5 projects for a median gap. Sorted by number of projects analysed.
Reproducible calculation: scripts/dld/aggregate_deliveries.py reads data/dld/registry.json (built by scripts/dld/aggregate_registry.py from the raw DLD files) and checks that every total adds up. The page and the CSV are regenerated with each register update.
Further reading
Frequently asked questions
How many off-plan projects in Dubai are past their declared end date?
As of November 1, 2026, 239 of the 1,061 active projects with a declared end date had passed it (22.5%), with 59,689 units and villas, according to the Dubai Land Department project register.
What share of off-plan projects is completed after the announced date?
Of the projects completed since 1 January 2025, 55.4% (133 of 240) were completed after their end date declared at the DLD. Across the whole register the share is 14.6%, but it understates the gap: for 1,102 projects, the recorded end date is exactly the completion date.
By how many months is the declared end date passed?
The median gap is 6.9 months for projects completed after the date since 2025, and 6.3 months for active projects past their date on November 1, 2026. 49 active projects are more than 12 months past their date.
What is the end date declared at the DLD?
It is the project end date recorded in the Dubai Land Department project register. It can be updated and the register keeps only the latest value, so it may differ from the date announced at launch and from the one in your sale and purchase agreement (SPA).
Why do so many projects have an end date equal to their completion date?
From 2010 to 2024, 77.8% of completed projects have a declared end date identical to their completion date. The register does not say why; these projects cannot show whether the original date was met. This is why the observatory highlights projects completed since 2025, whose two dates usually differ.
How can I check the progress of an off-plan project in Dubai?
The Dubai Land Department's Real Estate Project Status Enquiry service, also in the Dubai REST app, gives the status and completion percentage of a registered project. Our off-plan project pages also carry the register data: progress, declared end date and developer.
What happens to buyers when the end date is passed?
Payments go into the project's escrow account, which Law No. 8 of 2007 reserves for its construction. Any compensation depends on the clauses of the sale and purchase agreement (SPA): the law sets no scale. Our article on off-plan buyer rights covers the remedies.
Can I reuse the figures of this observatory?
Yes, freely, crediting "Source: Dubai Off-Plan Delivery Observatory, Cevitas Real Estate, based on the Dubai Land Department project register as of November 1, 2026" with a link to this page. The aggregated data can be downloaded as CSV.